The Dutch-Belgian High Speed Rail Debacle

We’ve been talking a lot about high speed rail lately here on PlaNYourCity. That’s not just because we like the subject, it’s also because it’s one of those dynamic topics that often seems to be in the news.

Last week brought us headlines about a high speed rail debacle over in The Netherlands and Belgium. The relatively new high speed rail service that connects these two countries, named Fyra, has been permanently suspended after a series of safety issues that plagued the service ever since it began its operations in 2009. But before we get into that, let’s take a look at the troubled history of Europe’s youngest high speed rail service.

Fyra is Swedish for four, and symbolizes the four cities that the service sought to connect: Amsterdam, Rotterdam, Antwerp and Brussels. €7 billion has been spent on the Dutch portion of the route, yielding a straight route between Amsterdam Airport and the Dutch-Belgian border, at parts sitting on concrete stilts and hovering above the flat Dutch landscape; at parts sunken into a trench so as to minimize the intrusion of the route (and noise from the train traffic) in urban areas. The route was also designed to allow trains to travel at speeds of up to 300 kilometers per hour. The Dutch state picked up the tab of the construction of the new tracks, which were also constructed to service the Thalys high speed rail service to Paris, in addition to the envisioned Fyra service to Brussels.

A Fyra train in The Netherlands, travelling on tracks designed specifically for a high speed rail connection between Amsterdam and Brussels. (Source: Reformatisch Dagblad, rd.nl).

A Fyra train in The Netherlands, travelling on tracks designed specifically for a high speed rail connection between Amsterdam and Brussels. (Source: Reformatisch Dagblad, rd.nl).

The Dutch High Speed Alliance or HSA (a joint venture between Royal Dutch Airlines and Dutch Railways) began to operate (or exploit) the Dutch portion of the route between Amsterdam and the Dutch border in 2009, years after the line was originally scheduled to be completed. (Service on the full route between Amsterdam and Brussels was to follow much later). To operate the high speed rail service on the Dutch portion of the route, the HSA would pay the Dutch government €148 million per year. What is more, the HSA, in which Dutch Railways has a 90% stake, originally offered to pay €178 million per year for the right to operate the route—more than twice the amount offered for the rights by foreign bidders. HSA offered this unjustifiably high amount out of fear that a foreign carrier would soon be providing train service in the Netherlands—a doom scenario that the monopolists at Dutch Railways had to avoid, at any cost.

The exceptionally high payment put HSA on the verge of bankruptcy. Indeed, the operator’s dire financial situation was to be the main reason why the decision was made to economize on the “rolling equipment”, or the trains that would service the route. In order to reduce the operational costs, HSA and the National Society for Belgian Railways opted to use cheaper and slower trains than typically seen on other European high speed rail routes. The Italian manufacturer AnsaldoBreda (an inexperienced newcomer to the industry) won the contract to supply the trains for the new service. After requesting qualifications from a host of train builders, AnsaldoBreda was eventually selected because of their competitive pricing. The price per seat of their trains was about half that of Siemens’ ICE trains, or Alstom’s TGV trains.

Looking back on AnsaldoBreda’s contracting, Dutch daily NRC Handelsblad reported in January that the HSA never had the intention to operate a “true” high speed rail service; a strong piece of investigative journalism stated that a speed of 220 kilometers per hour had been deemed sufficient for the Dutch portion of the route from the git-go by the HSA executives (by comparison, high speed rail service in Germany and France exceeds 300 kilometers per hour). Looking ahead to the opening of the full route between Amsterdam and Brussels, it became clear that the preferred model (AnsaldoBreda’s V220 trains) would not be able to reduce the travel time between these two cities as much as the operators had promised. Hence why a slightly faster model, AnsaldoBreda’s V250, was eventually selected to service the route—but only after the Dutch government pointed out that HSA had a contractual obligation to reduce the travel time by a certain margin, which the V220 model would not meet. And so, in 2004, the HSA placed an order for 19 V250 train sets with the Italian manufacturer.

The equipment was supposed to be delivered to the Dutch in 2007, but the inexperienced manufacturer failed to do so. When the equipment was finally delivered to The Netherlands in September of 2009, train service between Rotterdam and Amsterdam’s central stations could commence, over two years after the envisioned date. Starting with one train per hour on weekdays, service gradually expanded to weekends and holidays. By April 2011 service had increased to one train per 30 minutes, and the route had been extended to run between Amsterdam and the southern Dutch town of Breda. Finally then, on December 9th 2012, the full route between Amsterdam and Brussels was serviced.  Right from that day, the service was plagued by a myriad of technical issues.

In the first week, many runs between the two cities were cancelled; the ones that were not often incurred significant delays. It is estimated that half of all passengers in this first week of international service did not arrive on their destinations on time; two-thirds dealt with a delay of 15 minutes or more, and about 20% of passengers faced delays exceeding 30 minutes. Dutch Railways (and their Belgian counterparts) were flooded with complaints from passengers. The technical issues persisted, and even intensified over the course of the next month. On January 15th, half of all trains were cancelled due to broken equipment, whilst the other half of scheduled trains ran with an average delay of one hour. Due to wintry weather, 85% of all scheduled trains were cancelled two days later on January 17th. Facing security concerns and strong criticism from passengers and politicians alike, the Fyra was suspended indefinitely on January 18th—a little over a month since it first began servicing the originally envisioned route between Amsterdam and Brussels. Dutch Railways held manufacturer AnsaldoBreda responsible for the technical issues; AnsaldoBreda maintained that the issues were minor and would be resolved in a matter of days. However, a day later on January 19th it was announced that the technical issues with AnsaldoBreda’s V250 trains were not going to be addressed any time soon. At this point, 9 trains had already been delivered and the HSA had already paid €100 million euro to AnsaldoBreda, whilst the National Society for Belgian Railways had paid €35 million, ensuring that a lengthy legal battle between the manufacturer and the operators is ahead.

After some contemplation, the National Society for Belgian Railways dissolved their contract with AnsaldoBreda. On May 31st, the company’s CEO presented an impressive list of technical issues that engineering firms Mott McDonald and Concept Risk found with AnsaldoBreda’s V250 trains:

  • Large-scale problems with the infiltration of water in the trains;
  • Erosion and rustiness around the trains’ axels, with rust appearing on one particular axis after just a few kilometers had been traveled;
  • Poor fitting of the hydraulic and electrical cables onto the trains (these were placed on the bottom of the train, allowing it to incur damage due to the weight of the trains)
  • Technical differences between the various train sets, since the mechanics had each manufactured the train sets in their own ways;
  • Problems with the braking system, which was designed for speeds of up to 160 kilometers per hour, and not approved for use at speeds of up to 250 kilometers per hours (moreover, the wintry circumstances required an even lower speed, since the brake path was longer in wintry conditions)
  • The batteries, which are located under the passenger cabs, could ignite. There have been images of damage that occurred after a battery caught fire near the Dutch town of Watergraafsmeer. One image shows a burnt carpet on the floor of a passenger cab.
Rusty spots appeared around some train cabs’ axis after only a few rides. (Soucre: www.treinreiziger.nl).

Rusty spots appeared around some train cabs’ axis after only a few rides. (Soucre: http://www.treinreiziger.nl).

A Fyra train going unused near Rotterdam central station this past winter, due to the trains’ inability to function in wintry conditions. (Source: spitsnieuws.nl)

A Fyra train going unused near Rotterdam central station this past winter, due to the trains’ inability to function in wintry conditions. (Source: spitsnieuws.nl)

At the same time, manufacturer AnsaldoBreda continued to reject the CEO’s criticism, and threatened to sue the National Society for Belgian Railways for dissolving the contract. Days later, on June 3rd, Dutch Railways announced that it too would stop operating the V250 trains. With that decision, the Fyra service had come to a premature end just months after the service commenced. Now, the ads for the service have been removed and investigations into the contracting of AnsaldoBreda are on their way on both sides of the border.

fyra001

Information panel at Amsterdam Central Station: “No Fyra Amsterdam – Brussels until January 23rd. Mind the announcements. Also see http://www.nshispeed.nl” (Source: eenvandaag.nl)

This story is far from finished and it remains to be seen what consequences the manufacturer and the operators might face once the investigations have wrapped up. And whilst we don’t know much about the future of high speed rail in the Low Countries, we can already conclude that the story of the Fyra service is a textbook example of how not to plan and build a high speed rail system. It also is a poor use of the taxpayers’ euros, especially because the Dutch state had massively invested in a new, direct train route that it had partially built for the Fyra service to Brussels (as stated, the route is also used for the Thalys service to Paris, so the investment thankfully hasn’t been in vain). The Fyra-story also demonstrates that powerful corporate interests (in this case Dutch Railways’ desire to remain the sole rail service provider in The Netherlands) can abuse their position and waste an unbelievable amount of taxpayers’ money. It’s easy to imagine that, if a foreign provider would have been selected, they would have ended up paying the Dutch state less fees to operate train service along the route– leaving more funds available to properly invest in the rolling equipment.  (It’s also unlikely that a foreign operator, paying lower fees to for the rights to use the route, would have needed the financial aid that the HSA needed from the state to avoid going bankrupt.)

Finally, it also shows that, if you are planning on introducing high speed rail to a country or region, you probably don’t want to do so as half-heartedly (or should I say, “as cheap”) as the Dutch and the Belgians did it. Unless serious funds are going to be committed to bring high speed rail to a region, chances are, it will turn into a giant fiasco à la Fyra. (You get what you pay for.)

Tags: , , , , ,

One Comment on “The Dutch-Belgian High Speed Rail Debacle”

  1. freudje June 24, 2013 at 6:34 pm #

    Good summary of the Fyra soap! But you forgot to tell one thing: to make the high speed line feasible, the Belgian and Dutch railways first canceled all normal trains on the line, although they were very popular and much cheaper for travelers than Fyra or Thalys ever will be. The normal trains took 1 à 1,5 hour extra for the distance from Brussels to Amsterdam, but considering the price difference this was accepted happily by travelers. Because like this the (monopoly) train companies would compete their own, new, and very expensively paid for high speed lines, they just canceled the normal offer – which lead to a lot of protest even before any of the Fyra technical problems were known. In the first month that the Fyra was riding, suddenly the local trains on the track, that have a very slow speed but were cheap (and also more reliable) saw a huge increase in popularity… Also commuters complained a lot, because neither Fyra nor Thalys offered any subscription possibility.
    Just to point out: in a normal market, the Fyra would never have been feasible, as it couldn’t compete against the flexibility and good price of an ordinary train on the same track. Only by making it the only option left, the Fyra could survive – until it became clear that they were plain rubbish…

    Like

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: